Decision Maker: Cabinet member for development and infrastructure, and development management
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
To create sufficient budget from CIL funding to be used to enable Sinewave (an OFGEM registered specialist company), to lay cabling for a new power supply, from the Faringdon Leisure Centres/Schools external sub-station to the leisure centres dry side plantroom (£46,381.34) and any additional related infrastructure costs towards this project to a limit of £100,000.
The works to upgrade the power supply are essential if the Air Source Heat Pump (ASHP) and Solar Photovoltaic Cells (Solar PV) installation works are to progress.
Publication date: 12/07/2022
Date of decision: 08/07/2022
Effective from: 20/07/2022